 Contractor abandons Shs1.2b Mbarara road project over delayed payments

0-0x0-0-0#

By Aggrey Twesigye

M/s Jagens Technical Services has abandoned works on the Shs1.2 billion Makhan Singh–Major Victor Bwana road links in Mbarara City after City Council failed to release funds for the project.

Mbarara City Mayor Robert Mugabe Kakyebezi accuses Chief Finance Officer David Mbarekye of failing to release the money, resulting in the funds being returned to the Treasury and the contractor abandoning the site.

Kakyebezi accuses Mbarekye of causing City Council to breach its contract with M/s Jagens Technical Services, which was contracted to construct the Makhan Singh–Major Victor Bwana road links at a cost of Shs1.2 billion.

He says the contractor was expected to receive an advance payment equivalent to 30 per cent of the contract sum on June 19, 2026, but the funds were not released.

Kakyebezi says that despite the delayed advance payment, the contractor proceeded with the works and submitted an interim payment certificate worth Shs549 million on September 23, 2026. However, the contractor has reportedly not been paid despite completing the phase.

He says the breach of contract has prompted notices of intention to sue against the City Council from Jagens Technical Services, Evaristo Kategeya, who provided land for the road links, and traders at Makhan Singh Market over the incomplete works.

Kakyebezi says he has directed the internal auditor to examine the matter and petitioned the Inspectorate of Government (IGG) and the Rwizi Regional Criminal Investigations Department (CID) to investigate alleged financial irregularities and abuse of office by Mbarekye.

Mbarara City Council Speaker Bonny Tashobya has tasked Deputy City Town Clerk Simon Ejua with presenting a status report on the Makhan Singh–Major Victor Bwana road links project at the next council sitting.

Ejua confirmed that the funds had been returned to the Treasury but said he was uncertain when they would be reallocated for the intended works.

Mbarekye, who is accused of mishandling the project funds, said he was not authorised to speak to the media without clearance from his supervisor, the City Town Clerk.

He, however, says he is ready for investigations by any government agency, insisting that his documents are in order.

The contract, signed in June with a three-month completion period, was extended to November 30, 2026, but the project remains at 45 per cent completion, with six days remaining to the revised deadline.